All themes

Power & infrastructure

Who pays for new capacity, and who carries the risk?

Questions for the framework

These are questions to investigate and discuss, not adopted contract terms.

Contribute to this theme
  1. Who pays for grid upgrades and unused capacity?
  2. What happens if a project opens late or closes early?
  3. Would on-site generation, including rooftop solar, change the agreement?

Terms from the agreements

Lancaster AI Hub

Requires clean-energy sourcing, including eligible energy credits. Ten-year contracts at lower clean-energy shares can qualify with additional payments.

This summary uses the city’s draft. A signed copy has not been verified.

Section 3.3, page 7

Vantage Port Washington

The developer funds specified public improvements, subject to reimbursement arrangements, dedication and a two-year warranty. The agreement also addresses construction-related road repairs.

Approval verified; standalone final copy; signatures pending.

Section II.C.2, page 6

St. Louis Armory Data Center

Permit conditions require the project to fund its electrical infrastructure. The CBA term sheet calls for reasonable efforts to reach 50% renewable energy within five years, with localized renewable energy credits as a fallback.

The city has approved a permit. A signed community benefits agreement has not been verified.

Section Energy, page 2

Meta Beaver Dam

The company may explore solar, geothermal cooling and wind power but is not required to use them. If it submits plans, the city must promptly confirm whether those uses are permitted.

The public copy is effective December 9, 2024. City signatures appear on PDF page 20; Degas’s signature and attorney authentication appear on page 21.

Section 7(d), page 11

NTT Itasca CH3

The developer must provide security equal to 110% of the engineer’s estimate for required improvements. Accepted public water mains and fire hydrants become village infrastructure. A maintenance bond covers 10% of their cost for two years.

Public packet; signatures and final approval pending.

Section 8–10, page 6

Project Vanderbilt

The owner and developer pay development costs, including engineering, inspections, easements, permits and work required to correct deficiencies. A $209,045 financial guarantee secures work including stormwater, water main and Nasseff Way improvements.

The packet contains two instruments with blank signature/date fields. Tree mitigation differs: the development contract states 59 trees/$29,500; the final planned development exhibit states 58 trees/$29,000.

Section Development contract, Sections 6.1 and 9.1, page 17

Project Blue

Renewable-energy matching requires commercially reasonable efforts and annual verification. Utility or regulatory conflicts can limit the obligation; its remedies are consultation, a corrective plan and nonbinding mediation rather than damages or specific performance.

Approved; public copy county signature blank.

Section 3 and 6(c), page 6

Air Data Center

The customer may direct tax-offset grants to the county Utilities Department to pay project utility infrastructure costs. This is an option for using the grant, not a separate promise of free infrastructure.

The county-published copy is dated June 30, 2025 and includes signatures for Aeris Investments and the county on PDF page 6.

Section 1, page 2

Sky Data Center

The customer may direct tax-offset grants to the county Utilities Department to pay project utility infrastructure costs. This is an option for using the grant, not a separate promise of free infrastructure.

The county-published copy is dated June 30, 2025 and includes signatures for Skyward Holdings and the county on PDF page 6.

Section 1, page 2

SSDC1 Sulphur Springs

Electricity supplied outside Oncor’s lines triggers quarterly city payments of $0.002905 per kilowatt-hour, supported by certified interval data. The payment obligation continues while that supply arrangement operates, including after the agreement ends.

Registry reports effective May 9 2025; scan review pending.

Section 3.1.6.4, page 7

NE Edge Waterford

Host payments depend on a satisfactory binding power purchase agreement with Dominion. Qualifying delays in electricity delivery permit extensions with quarterly progress reports.

Historical 2023 public agreement. Payment obligations depend on occupancy, permits and other conditions; the stated amounts do not establish receipt by the town.

Section Section 13, page 11

Manor Farm, Poyle Road

Highway works must be completed before occupation. The developer also pays £15,000 for bus-stop improvements and £6,000 for traffic regulation before construction starts.

Council-published deed dated October 30, 2025. The inspected scan shows the council seal; the owner signature marks are not legible. Obligations depend on planning permission and commencement.

Section Schedule 3; definitions on pages 4 and 8, page 24

CRG Festus

The developer must enter an electricity agreement making it responsible for its energy use and all expanded electrical infrastructure needed for the project.

Posted ordinance and agreement; signature/date review pending.

Section I.A.5, page 6

Meta DeKalb

Each supply tier specifies 45 psi water pressure and a fire flow of 2,500 gallons per minute.

Approval recorded; original agreement and counterpart review pending; repeat fetch redirect loop, retrieval pending.

Section 2, page 3

Goldin DeKalb

The developer may have to extend the sanitary sewer at its expense and pay approximately $617,667.50 plus interest for an earlier extension. A recapture agreement can recover a proportionate share from later users.

City, owner and developer signatures visually verified across the separate counterpart pages 10–11. The original agreement is recorded as document 2023007068.

Section Section 4, added Section 8.3, page 6

Microsoft Goodyear

Microsoft must fund and construct the required water mains, wastewater discharge line, pumps and storage. If actual operations need more capacity than the engineering study assumed, Microsoft must pay for a new study and the additional improvements.

The city agenda includes the full fourth amendment as Exhibit 1 to Resolution 2023-2323. Its signature fields are blank; the operative text and engineering exhibits have been reviewed.

Section 6.2–6.3 and 6.6, page 11

Related agreements and records

Open each record for its source, status and missing documents.

Project Vanderbilt

Eagan, Minnesota

Renovation of an existing data center, with developer-funded infrastructure, stormwater safeguards and tree mitigation.

View agreement

Project Blue

Pima County, Arizona

Cooling requirements, renewable-energy commitments and phase-based community donations.

View agreement

NE Edge Waterford

Waterford, Connecticut

A historical proposal ties town payments to two data centers at Millstone, with construction deadlines, noise review and power-supply conditions.

View agreement

Goldin DeKalb

DeKalb, Illinois

A data center amendment reserves water capacity, funds utility extensions and discounts electricity tax subject to an annual minimum.

View agreement

What would you add?

Explain the change you would make, the community need it addresses, and any source that supports it.

Share a suggestion