CRG Festus

Infrastructure and funding agreement

Festus, Missouri

Festus publishes infrastructure and preliminary funding agreements for CRG’s proposed data center. The two documents cover different stages of the city’s funding and infrastructure arrangements.

Project party
CRG Acquisition LLC
Read original document

What’s included

Public revenue & benefits

Community payments are $3 million annually for abatement years one through five and $5 million for years six through ten. They depend on receiving the specified personal-property tax abatement. The first payment is advanced within 60 days of construction starting. A separate fire-station contribution is capped at $5 million.

Compare public revenue & benefits terms
Power & infrastructure

The developer must enter an electricity agreement making it responsible for its energy use and all expanded electrical infrastructure needed for the project.

Compare power & infrastructure terms
Water

The developer funds project-related water and sewer infrastructure, subject to agreed scope and cost. A later water-infrastructure plan must establish supply volumes and responsibilities. Private wells are prohibited, but public wells may serve the project.

Compare water terms
Land, noise & environment

The northeast ridge is protected from buildings, mass grading and clearing, with limited exceptions for investigation, drainage, emergency access and underground utilities that do not materially change its character.

Compare land, noise & environment terms
Reporting & enforcement

Most development and payment obligations depend on the developer electing to proceed. The agreement separately identifies obligations that take effect on signing and sets a distinct trigger for the fire-station payment.

Compare reporting & enforcement terms
About this document

Posted ordinance and agreement; signature/date review pending.

Document
Infrastructure and funding agreement
Published by
festusmo.gov
Parties
CRG Acquisition LLC
Reviewed
2026-09-07
Still needed
The later water-infrastructure plan, separate Port Authority instruments and evidence of payments and construction.