St. Louis approved a conditional-use permit for a data center at the Armory site in April 2026. The city also announced negotiated community-benefit terms, including a per-square-foot payment; the final community benefits agreement is still needed.

Document
Approval record & term sheet
Read the city’s approval announcement

What’s included

Water

The permit conditions call for air-cooled, closed-loop cooling. Before a building permit, the developer must enter a water agreement covering applicable fees, an impact study and any required remediation.

Compare water terms
Power & infrastructure

Permit conditions require the project to fund its electrical infrastructure. The CBA term sheet calls for reasonable efforts to reach 50% renewable energy within five years, with localized renewable energy credits as a fallback.

Compare power & infrastructure terms
Public revenue & benefits

The future CBA term sheet proposes $30 per square foot in community funding, estimated at $15.75 million. It also rules out local development incentives. These are proposed CBA commitments, not proof that payments have been made.

Compare public revenue & benefits terms
Jobs & local opportunity

The term sheet proposes 25 jobs in year one, 50 in year two and 100 thereafter for 20 years, with $2,000 per missing job. It also includes first-source hiring.

Compare jobs & local opportunity terms
Land, noise & environment

Permit conditions require annual independent noise testing at adjacent property lines and evidence of an R2-certified electronic-waste contractor. Generator testing is limited to specified weekday hours.

Compare land, noise & environment terms
Reporting & enforcement

A recorded CBA with the city’s redevelopment authority or another acceptable entity is a permit condition. The published CBA document describes terms for a future agreement.

Compare reporting & enforcement terms
About this document

The city has approved a permit. A signed community benefits agreement has not been verified.

Document
Approval record & term sheet
Published by
City of St. Louis
Parties
Final CBA parties require the final document.
Reviewed
2026-09-07
Still needed
The final recorded CBA and evidence of compliance with the permit conditions.