Hermantown’s proposed data center agreement with Harmony Group LLC sets out water service, road work and infrastructure responsibilities. The available draft also addresses tax abatement and remedies if commitments are missed.
- Project party
- Harmony Group LLC
- Public partner
- Hermantown, Minnesota
What’s included
Water
Lists potable-water demand up to 50,000 gallons daily, with temporary construction exceptions. During shortages, healthcare, public services and residential areas take priority.
Compare water termsPower & infrastructure
The developer pays for specified water, sewer and road improvements; city-requested extra capacity has separate cost rules.
Compare power & infrastructure termsPublic revenue & benefits
Anticipates a separate tax-abatement agreement for the project.
Compare public revenue & benefits termsReporting & enforcement
Describes default and remedies. It excludes third-party beneficiaries.
Compare reporting & enforcement termsAbout this document
This summary uses a draft. A signed copy has not been verified.
- Document
- Development agreement
- Published by
- City of Hermantown
- Parties
- City of Hermantown and Harmony Group LLC.
- Reviewed
- 2026-09-07
- Still needed
- The signed agreement, final permit, tax abatement agreement and infrastructure exhibits.